Kentucky Hydrocarbons/DPI

Performed preliminary engineering and cost estimating for expanding an existing 55 MMSCFD cryogenic gas plant to 65 MMSCFD and improving overall liquids recoveries. The new design achieves 95% propane recovery (15% increase plus product recovered meets more stringent specifications) and utilizes 4,000 Hp less than the original design at the lower throughput.